TEMPO.CO, Jakarta – PT Freeport Indonesia (PTFI) has yet to fully restore production capacity at its Grasberg mine following a landslide in September 2025, with output expected to reach only around 65 percent of normal capacity this year.
PTFI President Director Tony Wenas said the company is still conducting recovery work and ensuring safety across the mining area before gradually increasing production.
"Due to the landslide in September 2025, the production ramp-up process is progressing more slowly than our initial estimates. This year, production capacity is still around 65 percent," Tony said during a hearing with House of Representatives Commission XII on Tuesday, July 14, 2026.
Freeport Targets Full Recovery by End of 2027
PTFI aims to raise production capacity to around 75 percent in the first half of 2027 before returning to full capacity by the end of the year.
As mining operations recover, Freeport also expects its downstream facilities to increase output in line with the recovery of copper concentrate supply.
The company’s new smelter in Gresik, East Java, is targeted to produce around 600,000 tons of copper cathodes annually. Combined with PT Smelting Gresik, Freeport’s total copper cathode production capacity is expected to reach around 800,000 tons per year.
The Precious Metal Refinery (PMR) facility in the same area is also projected to produce up to 50 tons of gold annually by processing anode mud containing gold, silver, and other precious metals.
Grasberg Output Hit by DMLZ Suspension
From the mining side, Freeport estimates ore production in 2026 will average around 124,000 tons per day, down from approximately 139,000 tons per day in 2025.
Tony said the decline was mainly caused by the suspension of production at the Deep Mill Level Zone (DMLZ) mine following the landslide.
For 2026, PTFI targets producing around 800 million pounds of copper and 700,000 ounces of gold, equivalent to approximately 21 tons.
Tony projected production would gradually recover, reaching around 170,000 tons of ore per day in 2027, 208,000 tons per day in 2028, and 226,000 tons per day in 2029.
"That is our normal production level, or 100 percent capacity," Tony said.
Click here to get the latest news updates from Tempo on Google News
Freeport Submits 12% Stake Divestment Draft to Indonesian Govt
26 hari lalu

PT Freeport Indonesia (PTFI) has submitted a draft agreement on a 12 percent stock divestment to the government for the extension of the Special Mining License (IUPK).
Freeport Indonesia Pays Rp75 Trillion to State Budget
9 Mei 2026

The President Director noted that Freeport's contributions have the potential to climb further as mineral commodity prices remain relatively high.
Freeport Indonesia Targets Near-Full Output by End-2026 After Landslide
9 April 2026

Freeport Indonesia sets target for operations to return to nearly 100% by the end of 2026 following the landslide incident in the Grasberg Block Cave.
Freeport Indonesia Worker Fatally Shot at Grasberg Mine
11 Maret 2026

PT Freeport Indonesia reports a worker was killed in a shooting at the Grasberg mining site.
Freeport Extends Indonesia Contract to 2061 with $20bn Investment
20 Februari 2026

An investment agreement for the extension of Freeport's contract for the next 20 years is worth US$20 billion or around Rp337 trillion.
Indonesia to Gain 12% Extra Freeport Stake in New Deal
19 Februari 2026

Freeport-McMoRan agrees to increase Indonesia's ownership stake in PT Freeport Indonesia (PTFI) to 63% by 2041.
Indonesia to Extend Freeport Papua Mining Rights Past 2041
19 Februari 2026

In addition to licensing aspects, Freeport also stated additional commitments to the Papua community.
Gold Prices Forecast to Surge to Rp3.8 Million in 2026
24 Desember 2025

The gold price produced by PT Aneka Tambang, commonly known as Antam gold, was recorded at Rp2,596,475 per gram in trading today, Dec. 24, 2025.
Gold Prices Boost Freeport Indonesia's Revenue Despite Falling Production
24 November 2025

Freeport's current production is only about 70,000 tons of ore per day, which is 30 percent of its normal capacity of 210,000 tons per day.
Freeport Targets 1.3 Million Ounces of Gold by 2029 Amid Grasberg Mine Restart
19 November 2025

Freeport McMoRan targets a total gold production from PT Freeport Indonesia's mine in Central Papua to reach 1.3 million ounces in 2029.