PLN Ensures Swift Repair of Electrical Network Damaged by Aceh Flood

3 hours ago 1

December 2, 2025 | 11:33 am

TEMPO.CO, Jakarta - Indonesian state-owned electricity company, PT PLN (Persero), has deployed 500 technicians from various units across Indonesia to repair the damage to the 150-kilovolt (kV) transmission towers affected by the flood and landslides in Aceh. The dispatch of electrical technicians and logistics has been ongoing since Sunday, November 30, 2025, via land and air routes with the support of the Indonesian National Defense Forces (TNI).

PLN President Director, Darmawan Prasodjo, stated that the support from the Indonesian Air Force and Army has accelerated the process of restoring the damaged electrical network. "This collaboration is a crucial factor in expediting the transmission restoration," said Darmawan in a written statement on Monday, December 1, 2025.

Darmawan mentioned that the hundreds of technicians are currently stationed at several critical points to repair the 150 kV Arun-Bireuen SUTT towers (258 people), the 150 kV Bireuen-Peusangan SUTT (178 people), and the 150 kV P. Brandan-Langsa SUTT (64 people).

The flood and landslides in Aceh have caused road access to be severed, and several areas remain isolated. To ensure the timely arrival of materials and technical personnel, Darmawan stated that the Indonesian Air Force has assisted in airlifting using helicopters.

In addition to the air routes, PLN and the Indonesian Army operate trucks to reach areas that are still accessible by land. Emergency tower materials, technical equipment, and personnel logistics have started arriving at the affected locations.

Darmawan ensures that the recovery process is proceeding rapidly and safely. "Personnel are working nonstop to ensure that the electrical system is restored as soon as possible," he said.

Sumatra's PLN UIP3B General Manager, Amiruddin, stated that all emergency personnel and materials are already at the damaged tower area. He aims to complete the construction of emergency towers in the near future.

This recovery effort is being carried out after the main transmission network connecting several flood-affected areas suffered damage, disrupting the electricity supply at several points. "We are striving for the restoration of Aceh's power supply as quickly as possible," he said.

Editor’s Choice: Floods in Aceh: Several Areas Still Without Power, Residents Queue for Fuel

Click here to get the latest news updates from Tempo on Google News



5 Electricity Towers Collapse Due to Aceh Floods, Crippling 18 Regions

4 hari lalu

5 Electricity Towers Collapse Due to Aceh Floods, Crippling 18 Regions

The Aceh Disaster Management Agency (BPBA) recorded that as of November 26, floods had struck nine regencies/cities, including Bireuen and Aceh Utara.


PLN Requires Rp3,000 Trillion to Boost Indonesia's Power Generation Capacity

5 hari lalu

PLN Requires Rp3,000 Trillion to Boost Indonesia's Power Generation Capacity

The CEO of PLN stated that the 2025-2034 RUPTL sets a power capacity addition of 69.5 gigawatts.


Indonesia's PLN Plans 7 Waste-to-Energy Plant Projects in Major Cities

10 hari lalu

Indonesia's PLN Plans 7 Waste-to-Energy Plant Projects in Major Cities

The PLN CEO stated that seven projects for Waste-to-Energy Plant will be built in Medan, Tangerang, Semarang, Bogor, Bekasi, Yogyakarta, and Bali.


Aceh Broiler Farmer Sues PLN for Power Outages After 18,000 Chickens Die

15 hari lalu

Aceh Broiler Farmer Sues PLN for Power Outages After 18,000 Chickens Die

The Acehnese farmer's lawsuit against PLN stems from a series of power outages in late September 2025 that resulted in the death of 18,000 chickens.


Sumatra-Bangka Undersea Power Cable Network Fully Restored, Back in Operation

20 hari lalu

Sumatra-Bangka Undersea Power Cable Network Fully Restored, Back in Operation

The power transfer capacity from the Sumatra system to Bangka has increased from 60 megawatts (MW) to 100 MW.


Indonesia Channels Rp4.3 Trillion to Expand Rural Electrification

20 hari lalu

Indonesia Channels Rp4.3 Trillion to Expand Rural Electrification

Energy Minister Bahlil explained that the budget is part of the additional ministry budget of Rp6.28 trillion received in August 2025.


Bali's Ngurah Rai Airport Hit by Outage, InJourney Airports Apologizes

50 hari lalu

Bali's Ngurah Rai Airport Hit by Outage, InJourney Airports Apologizes

Around 42 international flights & 32 domestic routes have to adjust the departure & arrival schedules due to power outage in Bali's Ngurah Rai airport


Bali's Ngurah Rai Airport Hit with Hour-Long Power Outage

51 hari lalu

Bali's Ngurah Rai Airport Hit with Hour-Long Power Outage

PLN explained the cause of the one-hour-long blackout at I Gusti Ngurah Rai Airport, on Friday, October 10, 2025


Indonesia's PLN EPI to Build 5 Biomass Plants with Poland-Based Company G7

51 hari lalu

Indonesia's PLN EPI to Build 5 Biomass Plants with Poland-Based Company G7

Indonesia has the potential for approximately 130 million tons of biomass per year, but only a small portion is utilized.


Indonesia Uses Only 9.4 GW of Its 3,686 GW Renewable Energy Potential

55 hari lalu

Indonesia Uses Only 9.4 GW of Its 3,686 GW Renewable Energy Potential

PLN aims to shift its focus from fossil fuels to renewable energy, marking a 180-degree turn from its previous stance.


Read Entire Article
Parenting |